The Federal Air Transport Agency Approves the Commissioning of Terminal C at Sheremetyevo Airport
China Aviation Daily | Nov. 18, 2019
Sheremetyevo International Airport has received permission from the Federal Air Transport Agency to commission the renovated Terminal C (stage 1). The terminal is scheduled to open to the public in January 2020.
The new and improved Terminal C (stage 1) is part of the northern terminal group and is designed to handle international flights. It has a total floor area of 127,374 m2 and a throughput capacity of 20 million passengers per year. Terminal C (stage 1) also features indoor pedestrian passageway connecting it to a 5-level parking area with 2,500 spaces.
The design of Terminal C naturally combines the best tradition of Russian art and modern technologies. The interior features a Russian constructivist design.
The terminal features 84 check-in desks and 160 passport control booths to help process passengers, including layover passengers, as well as aircraft crews.
Currently, all the systems across the terminal are being checked and debugged. These works are being carried out by key units of JSC SIA, its subsidiaries, affiliated companies, and Aeroflot.
Contributed by Sheremetyevo International Airport